Originally posted by sbst272:Read today zaobao, on page 3.
This arh?
Originally posted by Tilldeath23:Anyone taking pics at Yishun??
Maybe This Friday
Originally posted by wenjie639:i read that... they are installing PSDs at Sengkang LRT Station.. Not really PSD but just some glass panels which stops ppl from falling onto the tracks, but someone did fell onto the tracks and killed by an incoming train...
Yeah, that's the other known LRT fatality.
Update: 2nd set of PSD up on Yishun SB platform.
Progress is so slow at Yishun? PSR gets 3 PSDs per night, making the total 21+9, as of today.
Originally posted by jcqh:Progress is so slow at Yishun? PSR gets 3 PSDs per night, making the total 21+9, as of today.
maybe they focusing more on PSR first lol. Wonder why they decided to do it 21+9 instead of doing like 15+15 or 24+6. hmm.
Originally posted by jcqh:Progress is so slow at Yishun? PSR gets 3 PSDs per night, making the total 21+9, as of today.
No progress at Yishun yet... only hav 2
Originally posted by wenjie639:i read that... they are installing PSDs at Sengkang LRT Station.. Not really PSD but just some glass panels which stops ppl from falling onto the tracks, but someone did fell onto the tracks and killed by an incoming train...
But the PSDs to me won't help.
In some occassionally cases, they can still go into the holes :) It's just to not let them fall because of the "wind" from the stocks
28/08/09's update:
Another 3 PSDs at PSR.
Total is now 21+12.
UPDATE : Yishun has 2 PSD sets.
Originally posted by wenjie639:No progress at Yishun yet... only hav 2
Jurong East even worst , none!
Originally posted by Bus and Train LoVuR:UPDATE : Yishun has 2 PSD sets.
Posted twice already lozl.
Yishun PSD (no updates, only 2 as of today):
+3 for PSR today.
Total: 21+15
Yishun no updates today... still 2...
No works on Saturday and Sunday, today +3
Total: 21+18 (Sets on Platform A + Sets on Platform B)
Yishun has 4 as of now. However, I am not very sure.
Jurong East stil NONE.. -.-'
Originally posted by Mercedes Benz O305:Jurong East stil NONE.. -.-'
Maybe Jurong East is the last station to get PSD among the three,.
Originally posted by Bus and Train LoVuR:Maybe Jurong East is the last station to get PSD among the three,.
should be...
Originally posted by willis_chong:Yishun PSD (no updates, only 2 as of today):
Looks prominent from this view.....
Yishun +2 today, which makes total of 6 sets now.
Pasir Ris Updates.
In total Platform A and Platform B, 4 more sets to complete the whole set of PSDs in Pasir Ris. WOOHOO!
Originally posted by willis_chong:Yishun +2 today, which makes total of 6 sets now.
yah... i saw it just now
Hope Jurong East will start putting up PSD by mid-september/ end-september.