Installation of half-height PSDs in above-ground MRT stations
1. PSR - 48.5 (24.5 + 24)
2. YIS - 48 (24 + 24)
3. JUR - 10 (6 + 4 + 0 + 0)
yea! Juorng East got 6 sets! on westbound
When does its installed?
yesterday or...
i saw it the previous day.
Originally posted by Khairiano:yea! Juorng East got 6 sets! on westbound
The Staff keep asking ppl to stand behind the yellow line when ppl are standing behind those half-height PSDs
Originally posted by brotherchen1982:The Staff keep asking ppl to stand behind the yellow line when ppl are standing behind those half-height PSDs
yeah.. saw that while i was on the way home =)
Just to ask:
Does the PSD closes the door currently? Coz i actualy saw doors at the back of the PSD while i was on 219/220 yesterday.
Jurong East middle platform has been installed some PSDs already!
Originally posted by BiminiRosy:Jurong East middle platform has been installed some PSDs already!
Yup , 2 of them , spotted it with jcqh.
Note: The order of the PSDs written on the list is platform A, then B, and A B C D for Jurong.
PSR has a new panel now (will upload pic later).
Originally posted by SBS8214Z:Just to ask:
Does the PSD closes the door currently? Coz i actualy saw doors at the back of the PSD while i was on 219/220 yesterday.
Not yet. They have not been fully installed.
Today's pics:
PSR
JUR
If another PSDs installed, please update in Page 13 Post 1
Originally posted by jcqh:Today's pics:
PSR
Now cannot take any good videos at PSR anymore , thought that the front will still be the same but NO!
I wonder if they will remove the tactile studs along the platform edge since with the psd retrofit they have been made redundant.
I believe that the 2 PSDs at middle platform of JE is platform D, not B
The sequence should be A C D B, not A B C D
correct me if i'm wrong
Originally posted by azharjj:I believe that the 2 PSDs at middle platform of JE is platform D, not B
The sequence should be A C D B, not A B C D
correct me if i'm wrong
Originally posted by Khairiano:
Yea.. The middle platform is C & D =] middle platform got 4 set so there are 10 sets (wb & middle platforms)
At the end right?
Originally posted by Bus and Train LoVuR:At the end right?
yes.. =)
Originally posted by jcqh:Note: The order of the PSDs written on the list is platform A, then B, and A B C D for Jurong.
PSR has a new panel now (will upload pic later).
Not yet. They have not been fully installed.
Today's pics:
PSR
JUR
shld be A C D B... i mean the sequence
Originally posted by ignoramuses:I wonder if they will remove the tactile studs along the platform edge since with the psd retrofit they have been made redundant.
don't think they would...there's no point spending the money to do it. not like as if its doing any harm there.
JUR station is super busy all the time.. Everytime i see ppl standing beyond the yellow line
Originally posted by Khairiano:
yes.. =)
Luckily not the front.
any new additions of PSD at JUR today??
Originally posted by smrt3099:any new additions of PSD at JUR today??
yes.. added 3 more sets on westbound.. so there are 9 sets on westbound, 4 sets on middle platform so become 13 sets altogether
Please update in Page 13 Post 1
I saw some PSDs in JUR platform already