Originally posted by Novawin™:
Hey guys,
Just want to find out about the opening of CCL Stage 2 to public. Will it be opened in 2008? Or we have to wait until all stage is completed in 2010 to be opened?
It seemed there is no details on LTA website at the moment. But I do hope they will open Stage 2 in 2008.
You are right that LTA is keeping mum on the opening schedule. The original schedule is to open the stages in sequence, starting from Stage 1 in 2007 to Stage 5 in 2010. However due to the Nicoll Highway incident, LTA has not make any concrete announcement on the revised schedule.
However, we may infer how the it will open based on proxy source. A close proxy is
Circle Line Art Competition, where LTA invites artwork/design to be incorporated into the new Circle Line system. The competition has two phases: first phase for stations in Stage 1-3, and second phase for Stage 4-5. Hence, we can infer that it is most likely that Circle Line will be opened to public in two phase: Stage 1-3 then Stage 4-5.