Originally posted by SG1131L:btw, yesterday I thought I heard over the radio that the Jurong Region Line is cancelled. It was proposed to be elevated, 20km. but now the authorities are looking at replacing the proposed Jurong Region Line with other new lines, for more economic effectiveness (�济效益). research works already carried out for parts of the line will be re-used. And plans will be announced in the later part of this year when the LTMP 2018 is announced.
that’s what I thought I heard over the radio yesterday, but when I looked at the internet, I couldn’t find anything about it. so most probably I’m imagining things.
Huh? I purposely buy BTO in Jurong, hoping for JRL
Originally posted by ND323F:Huh? I purposely buy BTO in Jurong, hoping for JRL
Even if it happens, im still confident that there will be at least a railway network there
Originally posted by SG1131L:already said I’m imagining things. #FakeNews
Can you don’t be like gekpohboy please...
Originally posted by carbikebus:Can you don’t be like gekpohboy please...
Okay
Originally posted by carbikebus:Can you don’t be like gekpohboy please...
For all we know he is Gek Poh Boy.
Things to expect in 2019
1st half of 2019 - Opening of Jewel Changi Airport (source)
March - Opening of Yishun Bus Interchange (Northpoint City, which contains Yishun bus Interchange, opened in December 2017. Earlier bus interchanges at Boon Lay, Bedok and Bukit Panjang opened 1 year after their host shopping centre opened. If Yishun Bus Interchange doesn’t open in December 2018, it’s highly likely that the opening is in March 2019 during the March school holidays.)
June - Opening of Canberra MRT Station (source 1)(source 2)(mid-2015 + 48 months = mid-2019)
November - Opening of Jurong East 2nd Temporary Bus Interchange (expected completion date: 25 August 2019)(source)
December - Opening of Woodlands Regional Bus Interchange (expected completion date: 30 September 2019)(source)
December - Opening of Thomson-East Coast Line Stage 1 (best guess)
* Testing and commissioning of bus interchange/terminal takes 2 months. Reference: Shenton Way Bus Terminal obtained Temporary Occupation Permit on 11 April 2017 (source) and opened on 25 June 2017. (source) This is how I estimate the opening months of the second Jurong East Temporary Bus Interchange and Woodlands Regional Bus Interchange.
This is what I am able to gather about 2019, based on the information that is available as of now.
Feel free to add on to the list as more information becomes available.
From the looks of it, 2019 is going to be an exciting year which would see the opening of 3 bus interchanges (Yishun, Jurong East, Woodlands) and 4 MRT stations in the North (Canberra station on the NSL and Woodlands North, Woodlands and Woodlands South stations on the TEL).
Really looking forward to 2019.
Spotted Euro 6 MAN double deck in STK
Originally posted by iveco:For all we know he is Gek Poh Boy.
IKR..
Originally posted by SG1131L:December - Opening of Thomson-East Coast Line Stage 1 (best guess)
Yup TEL1 scheduled to open around Q4 2019.. According to the Thomson Line Construction blog..